Accomplishment33%34%34%35%36%36%37%36%35%34%33%against 41% plannedplanned
Cash flow₱9.53Mbilled vs disbursed
Cost by tradeConcreteSteelEarthworksFinishes6 trades
Progress33343435363637363533%vs 41% planned
Billing No. 4Certified to date₱2.53MRetention 10%₱253,768This claim₱861,400statement of work accomplished
Backlog4%5%5%6%5%4%behind programme
DeliveriesCement420 bagsRebar12.4 tAggregates38 m³received this week
ManpowerMPJDBSALTR44454647484849484744on site today
EquipmentExcavatorMixerCrane9 units on hire
Non-conformance2open · 1 closed
Weather2 days3 days3 days4 days2 dayslost, force majeure